Project

GM Yuma

Categories

Modular Electric,

Client

GM Yuma

Description

Battery Charging Sub Station.

Location

GM Proving Grounds – Yuma, Arizona

Challenge

Complete the substation 4 weeks after gear arrival. The electrical equipment was delayed in manufacturing by the gear manufacturer, and the general contractor needed to turn the project over to GM within 6 weeks of receiving gear.

Solution

⦁ Flex Air designed and engineered a modular enclosure for the gear.
⦁ The enclosure was ready on the manufacturing floor when the gear arrived.
⦁ Shipped a “turnkey” unit within 4 weeks of receiving gear.